In Design: Route 50 Corridor Improvements in Fairfax and Loudoun Counties
Cost and schedule ►
This project will make safety and operational improvements at several locations along a six-mile stretch of Route 50 (John S. Mosby Highway) between Gum Spring Road (Route 659) and Centreville Road (Route 657).
Route 50 averages up to 71,000 vehicles a day within the project limits.
Estimated Costs
Preliminary Engineering: $1.3 million
Construction: $9.4 million
Total: $10.7 million
The project is financed with federal, state (including Smart Scale) and Loudoun County funding.
Benefits
The project aims to relieve congestion and improve safety and operations.
Major Milestones
Begin Preliminary Engineering: April 2019
Begin Construction: To be determined
Resources
              
                    W. Calvin Britt, P.E.
Location & Design
                    703-259-2961
                    
              
                    Kimberly McCool, P.E.
Preliminary Engineering
                    703-259-3220
                    
Phase: In Design
UPC: 114827, 114828
State ID: 0050-053-211, P101; 0050-M10-010, P101
                Lat/Long: 38.911217, -77.473252
                
              
              
                
                
                Locality:
                
                Fairfax
                
                
        and
       
                
                
                Loudoun
                
                
                
                
            