In Design: North Old Glebe Road over North Glebe Road Bridge Replacement in Arlington County
Cost and schedule ►
Public outreach ►
This project will replace the North Old Glebe Road bridge over North Glebe Road (Route 120). The bridge, which averages 7,000 vehicles a day, was built in 1964.
A new bridge will be constructed due to the estimated rehabilitation cost of the existing bridge exceeding 65% of the estimated cost to replace the bridge.
The new bridge will feature a wider sidewalk on the eastern side and an additional sidewalk on the western side.
Estimated Project Costs
Preliminary Engineering - $1.5 million
Construction - $13.5 million
Total - $15 million
The project is financed with federal and state funding, including State of Good Repair funds used for bridges.
Benefits
This project will:
- Improve driver and pedestrian safety
- Maintain driver mobility
- Enhance pedestrian mobility via the additional sidewalk
- Reduce maintenance costs
Major Milestones
Virtual Public Information Meeting - October 2023
Design Public Hearing - Late 2024
Advertise for Construction - Early 2027
Begin Construction - Mid-2027
Resources
              
                    Dipali Patel, P.E.
Structure & Bridge
                    703-259-2429
                    
              
                    Minwoo Ha, P.E.
Preliminary Engineering
                    703-259-2207
                    
Other relevant links:
Virtual Public Information Meeting - 
October 2023
Major funding source: State of Good Repair
Phase: In Design
UPC: 119204
State ID: 6743-000-914, B610, P101, R201
Federal ID: NHPP-5B01 (257)
                Lat/Long: 38.925936, -77.122202
                
              
              
                
                
                Locality:
                
                Arlington
                
                
                
                
            